Minimum Requirements
The minimum requirements for lifting and cranage are:
# | Requirement |
---|---|
LC1 | Prior to conducting a crane lift, the site must be assessed for hazards that may impact the work and incorporated into the Lift Plan. |
LC2 | All cranes, hoists, lifting gear and taglines are suitable for the task and the load characteristics. |
LC3 | All personnel involved in a crane lift are qualified and assessed for competency in their role for the different types, capacities and operations of cranes. |
LC4 | Exclusion zones must be established using continuous physical barriers. |
LC5 | Lifting activities will be conducted and controlled in accordance with documented lifting operations and safe systems of work. |
LC6 | All loads must be suitably contained, correctly packaged and restrained prior to lifting. |
LC7 | Where crane operators work at height, a rescue plan must be documented and tested. |